LEVEL 4 – FUNCTIONAL TESTING
4 級 – 功能測試
R2
Level 4, managed and delivered by the Owners Commissioning Consultant, with support from the General Contractor, focuses on bringing the systems together, integrating them, and conducting a series of rigorous tests to ensure their alignment with the Owner's Project Requirements [OPR], Basis of Design [BOD], and relevant contract documentation such as drawings, specifications, and control logics. This stage plays a pivotal role in verifying the functional performance of these integrated systems.
第 4 級由業主試運轉顧問在總承包商的支援下管理和交付,重點是將系統組合在一起、整合並進行一系列嚴格的測試,以確保其與業主的專案要求 [OPR]、設計基礎 [BOD] 以及相關合約文件(例如圖紙、規範和控制邏輯)保持一致。 此階段在驗證這些整合系統的功能性能方面發揮關鍵作用。
R3
Step
步驟
Task/Activity
任務/活動
Status
狀態
R4
L4-01
L4-01
Write and Issue Scripts that will be used to facilitate the testing works.
編寫和發布用於促進測試工作的腳本。
To Be Completed
待完成
R5
L4-02
L4-02
Write and Issue Work Permits as noted in Level 0 that will be used to facilitate the works.
編寫並頒發 0 級中註明的工作許可證,用於促進工作。
To Be Completed
待完成
R6
L4-03
L4-03
Ensure that Temporary Equipment and Instruments are installed in line with the approved Load Bank & Equipment Plan as noted in Level 0 works.
確保臨時設備和儀器的安裝符合 0 級工程中所述的核准的負載庫和設備計畫。
To Be Completed
待完成
R7
L4-04
L4-04
Operate Temporary Equipment and Instruments to facilitate the testing works.
操作臨時設備和儀器以方便測試工作。
To Be Completed
待完成
R8
L4-05
L4-05
Plan and Manage Testing and Acceptance of plant, equipment, and systems in line with approved procedures, scripts, and programme.
根據批准的程序、腳本和計劃,規劃和管理工廠、設備和系統的測試和驗收。
To Be Completed
待完成
R9
L4-06
L4-06
Complete Thermographic Studies and create report as noted in Level 0 works.
完成熱成像研究並創建 0 級作品中所述的報告。
To Be Completed
待完成
R10
L4-07
L4-07
Download Data and Information for review after testing.
下載資料和資訊以供測試後查看。
To Be Completed
待完成
R11
L4-08
L4-08
Update Commissioning Tracking to reflect actual status and progress. [Manually or as per Commissioning Electronic Platform]
更新試運轉追蹤以反映實際狀態和進度。 【手動或依電子平台試運轉】
To Be Completed
待完成
R12
L4-09
L4-09
Add any issues to Observation Register and managing to close.
將任何問題添加到觀察登記冊並設法關閉。
To Be Completed
待完成
R13
L4-10
L4-10
File and manage documentation and records within the Project electronic filing system
在專案電子歸檔系統內歸檔和管理文件和記錄
To Be Completed
待完成
R14
L4-11
L4-11
Issue regular 2 Week Look Ahead Schedules for Commissioning Team Resource Planning.
定期發布 2 週展望時間表以進行試運轉團隊資源規劃。
To Be Completed
待完成
R15
L4-12
L4-12
Conduct Daily Morning Coordination Workshop.
舉辦每日早晨協調研討會。
To Be Completed
待完成
R16
L4-13
L4-13
Provide Daily Commissioning Updates.
提供每日試運轉更新。
To Be Completed
待完成
R17
L4-14
L4-14
Conduct Commissioning Focused Weekly Meetings and Workshops.
舉辦以試運轉為重點的每週會議和研討會。
To Be Completed
待完成
R18
L4-15
L4-15
Provide Commissioning Focused Reports. [Level 4 / Monthly / Weekly]
提供試運轉重點報告。 [4級/每月/每週]
To Be Completed
待完成
R19
L4-16
L4-16
Issue Final Operation and Maintenance Manuals.
發布最終操作和維護手冊。
To Be Completed
待完成
R20
L4-17
L4-17
Start Facility Operatives Training in line with the documents noted in Level 0 works.
根據 0 級工程中註明的文件開始設施操作員訓練。
To Be Completed
待完成
R21
L4-18
L4-18
Install all Blue Tags where applicable.
安裝所有適用的藍色標籤。
To Be Completed
待完成
R22
L4-19
L4-19
Provide to Owner, Level Close Out Reports.
提供業主平整收尾報告。
To Be Completed
待完成
R23
L4-20
L4-20
Sign off Level.
簽核等級。
To Be Completed
待完成
來源:066 Data Center Commissioning Checklist R4.xlsx / 繁中翻譯版