LEVEL 2 – Component Delivery, Installation & Pre-Startup
2 級 – 組件交付、安裝和預啟動
R2
Level 2, managed by the General Contractor, is a crucial stage in the data centre commissioning process, aimed at ensuring that all equipment, plant, and components are successfully delivered, installed, and thoroughly checked via pre-start-up activities to meet the project requirements. This stage sets the foundation for the subsequent energization phase at Level 3.
2 級由總承包商管理,是資料中心試運轉過程中的關鍵階段,旨在確保所有設備、廠房和組件透過啟動前活動成功交付、安裝和徹底檢查,以滿足專案要求。 此階段為後續 3 級通電階段奠定基礎。
R3
Step
步驟
Task/Activity
任務/活動
Status
狀態
R4
L2-01
L2-01
Write and Issue Level 2 Checklists and Scripts that will be used to facilitate the works.
編寫並發布用於促進工作的 2 級清單和腳本。
To Be Completed
待完成
R5
L2-02
L2-02
Plan and Manage Deliveries of plant, equipment, and materials. [If not, Factory Tested]
規劃和管理工廠、設備和材料的交付。 [如果沒有,則經過工廠測試]
To Be Completed
待完成
R6
L2-03
L2-03
Complete Delivery and Storage Checklists when plant, equipment and materials arrive on site.
當工廠、設備和材料到達現場時,填寫交付和儲存清單。
To Be Completed
待完成
R7
L2-04
L2-04
Complete Installation Checklist Inspections.
完成安裝檢查表檢查。
To Be Completed
待完成
R8
L2-05
L2-05
Complete Pre-Start-up / Energization Inspections.
完成啟動前/通電檢查。
To Be Completed
待完成
R9
L2-06
L2-06
Conduct any First of Kind [FOK] Inspections if noted in the project process with the owner’s CxP.
如果業主 CxP 在專案流程中註明,則進行任何首次 [FOK] 檢查。
To Be Completed
待完成
R10
L2-07
L2-07
For Electrical Panels ensure Arc Flash Stickers are attached and Breakers Set in line with the Arc Flash Report and Discrimination Study.
對於電氣面板,確保貼有弧閃貼紙並設定符合弧閃報告和歧視研究的斷路器。
To Be Completed
待完成
R11
L2-08
L2-08
Complete Foreign Object Detection [FOD] Inspection for all electrical panels and equipment.
對所有電氣面板和設備進行完整的異物檢測 [FOD] 檢查。
To Be Completed
待完成
R12
L2-09
L2-09
Update Commissioning Tracking to reflect actual status and progress. [Manually or as per Commissioning Electronic Platform]
更新試運轉追蹤以反映實際狀態和進度。 【手動或依電子平台試運轉】
To Be Completed
待完成
R13
L2-10
L2-10
Manage the Overall Programme for the Commissioning Tasks and Activities.
管理試運轉任務和活動的總體計劃。
To Be Completed
待完成
R14
L2-11
L2-11
Add any issues to Observation Register and managing to close.
將任何問題添加到觀察登記冊並設法關閉。
To Be Completed
待完成
R15
L2-12
L2-12
File and manage documentation and records within the Project electronic filing system.
在專案電子歸檔系統中歸檔和管理文件和記錄。
To Be Completed
待完成
R16
L2-13
L2-13
Issue regular 2 Week Look Ahead Schedules for Commissioning Team Resource Planning.
定期發布 2 週展望時間表以進行試運轉團隊資源規劃。
To Be Completed
待完成
R17
L2-14
L2-14
Conduct Daily Morning Coordination Workshop.
舉辦每日早晨協調研討會。
To Be Completed
待完成
R18
L2-15
L2-15
Provide Daily Commissioning Updates.
提供每日試運轉更新。
To Be Completed
待完成
R19
L2-16
L2-16
Conduct Commissioning Focused Weekly Meetings and Workshops.
舉辦以試運轉為重點的每週會議和研討會。
To Be Completed
待完成
R20
L2-17
L2-17
Provide Commissioning Focused Reports. [Monthly / Weekly]
提供試運轉重點報告。 [每月/每週]
To Be Completed
待完成
R21
L2-18
L2-18
Install all Yellow Tags where applicable.
安裝所有適用的黃色標籤。
To Be Completed
待完成
R22
L2-19
L2-19
Provide to Owner, Level Close Out Reports.
提供業主平整收尾報告。
To Be Completed
待完成
R23
L2-20
L2-20
Sign off Level.
簽核等級。
To Be Completed
待完成